ACA - Pilot Program - "Scheduled Phases"

Typical Year - Proposed Schedule:

The following proposal details the phases in the proposed schedule, which would take place in any given year.

SAMPLE - Fiscal 2009-2010

Sample Year - Fiscal 2009-10
Fiscal Year
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
Jan - Feb - March
April - May - June
July - Aug - Sept
Oct - Nov - Dec

2008-09

(previous)

Close-out

(previous year projects)
     

2009-10

(current)

Tender & Award

Implementation

Implementation

Implementation

2010-11

(next year's projects)

Schematic Planning

Capital Plan Submitted to Executive

Detailed Planning

Detailed Planning

2011-12

(future projects)
   

ID & Prioritize

Schematic Planning

 

Phase Descriptions:

Identify, Prioritize, Schematic Planning Phase (1 to 9 months)

This phase compiles the ACA projects in preparation for approval submission.

  • reviews projects requests submitted,
  • prioritizes the projects with pre estimates,
  • schematic planning of priority projects takes place,
  • updated estimates,
  • Review of priority projects in coordination schematic planning.

To Executive Review and Approval Phase(1 to 3 months)

This phase see the submission of the ACA Minor Capital projects identified and preplanned in the previous phase.

Detail Planning Phase (1 to 6 months)

Projects approved are taken forward to detail planning.  Once details estimates are completed a final program review is completed to balance any preplanning discrepancies.

  • engage designers
  • detail estimates
  • tender documents
  • Program review

Tender and Award Phase (1 to 3 months)

Projects are tendered and awarded for construction. A project budget review takes place to balance and estimated discrepancies.

Project Implementation Phase (1 to 9 months)

Approved projects taken through construction.

Project closeout Phase (1 to 3 months)

With construction now complete the facility information is updated through an as-built process.

  • facility inventory updated,
  • maintenance manual and drawing information updated,
  • Project files are archived