November 2009 to January 2010
- Concrete is poured for the first wall
- More framework and walls are erected
-Walls for the entire first floor are nearly complete
*click on images for larger views
October 2009
- Ledcor Construction begins erecting framework for foundations
*click on images for larger views
June 2009
-Site preparation has begun
-Project is out to tender