Skip to main content - Skip to contact information

ICSS Building Construction Updates

Click here to view ICSS drawings and details. Click on images below for a larger image.

 January 2011

  • Building completed
ICSS Bldg ICSS Bldg ICSS Bldg ICSS Bldg
ICSS Bldg ICSS Bldg ICSS Bldg

 

September 2010

  • Building nearing completion
  • Siding being installed
siding    

 

July to August 2010

  • Ducting, plumbing and electrical being installed
  • Roof and second floor walls completed
ductwork roof more boarding
boarding    

 

May to June 2010

  • Backfilling, mechanical and electrical rough ins
  • Block and steel stud wall construction
  • Painting
office hallway block walls
more block workers second floor
steel inside second floor  

 

April to May 2010

  • Steel structure for second level walls and roof is installed
  • Second level concrete floor and roof are poured
Starting the steel structure Second level steel Steel continued
Corner shot of steel structure Starting the roof Roof completed

 

March 2010

  • Hollow-core second level floor is installed
Crane for placing hollow-core slabs for second level Placing hollow-core slabs Hollow-core floor

 

February 2010

  • First level walls completed
  • Plumbing and electrical groundworks completed
  • First level concrete floor is poured
Last of the first floor forms being removed Completed first floor walls Tank preparation
Preparing to pour first level floor

  

November 2009 to January 2010

  • More forms are erected
  • Foundations are all poured
  • Concrete walls are poured for almost the entire first level
Wall Construction First floor forms First floor walls continued...
Continued... Forms Setting up more forms
Finished walls, more foundations Rebar in wall Nearly all first floor walls are complete

 

October 2009

  • Ledcor Construction begins erecting forms for foundations and walls
Foundation hole Foundation Forms Forms
Back Wall Form Installing rebar More rebar
Concrete Pumper Truck    

 

June 2009

  • Site preparation has begun
  • Project is out to tender
  • Construction is slated to begin in Summer 2009