ICSS Building Construction Updates
Click here to view ICSS drawings and details. Click on images below for a larger image.
January 2011
- Building completed
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
September 2010
- Building nearing completion
- Siding being installed
![]() |
July to August 2010
- Ducting, plumbing and electrical being installed
- Roof and second floor walls completed
![]() |
![]() |
![]() |
![]() |
May to June 2010
- Backfilling, mechanical and electrical rough ins
- Block and steel stud wall construction
- Painting
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
April to May 2010
- Steel structure for second level walls and roof is installed
- Second level concrete floor and roof are poured
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
March 2010
- Hollow-core second level floor is installed
![]() |
![]() |
![]() |
February 2010
- First level walls completed
- Plumbing and electrical groundworks completed
- First level concrete floor is poured
![]() |
![]() |
![]() |
![]() |
November 2009 to January 2010
- More forms are erected
- Foundations are all poured
- Concrete walls are poured for almost the entire first level
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
October 2009
- Ledcor Construction begins erecting forms for foundations and walls
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
June 2009
- Site preparation has begun
- Project is out to tender
- Construction is slated to begin in Summer 2009